To install LV switchgear on a project connected to the Sharjah Electricity, Water and Gas Authority (SEWA) network, the panels generally have to come from an assembler that SEWA has registered for that category and rating, and the panel design goes through consultant and authority review before manufacture. Al Qudrah Switchgear, based in Sharjah, UAE, is a SEWA Certified Company, Grade 1, for switchgear assembly and capacitor bank components up to 3200 A. This article covers what that means for a project and what a clean submittal looks like.
Why does SEWA register panel builders?
SEWA registers switchgear assemblers so that the boards connected to its network come from factories it has assessed. A registered company has shown the authority its facilities, its quality system and its capability for the categories it is listed under.
For a developer or contractor, the practical effect is simple. If the panel builder is not on SEWA's list for the type and rating of board the project needs, the submittal is likely to be stopped before anyone looks at the drawings. Checking registration is the first step, not the last.
Registration rules, categories and the documents SEWA asks for can change. Always confirm the current requirements with SEWA and the project consultant rather than relying on an older project's file.
What does a Grade 1 registration up to 3200 A mean?
The grade and rating describe the scope SEWA has accepted for a company. Al Qudrah's registration is Grade 1 for switchgear assembly and for capacitor bank components, up to 3200 A, which covers main distribution boards, SMDBs, DBs and power factor correction panels within that rating.
That rating lines up with our design verification. Our MDB designs are verified to IEC 61439-2 by DEKRA and ASTA (Intertek) up to 3200 A, with short-circuit withstand of 65 kA for 3 s. In other words, the authority registration and the type-test evidence cover the same range, which makes review simpler.
For government work in Sharjah, a second registration often matters: we are also a first-category registered supplier with the Sharjah Directorate of Public Works, and a registered supplier of switchgear and control gear with the UAE Ministry of Energy and Infrastructure.
What goes into a SEWA panel submittal?
A SEWA panel submittal usually brings together company documents, design documents and test evidence for the specific boards on the project. The consultant reviews it first, and the authority then reviews what it needs to see.
Typical contents, which we adjust to the consultant's and SEWA's current checklist:
- Cover letter and compliance statement against the specification, clause by clause.
- Copy of the SEWA registration certificate and trade licence.
- Single-line diagrams for every board, with ratings, breaker types and settings.
- General arrangement drawings showing dimensions, IP rating, form of separation and the metering compartment.
- Schematic and wiring diagrams for control and metering circuits.
- Bill of materials with makes and catalogue numbers.
- IEC 61439-2 design verification certificates and test reports for the offered design.
- Busbar sizing and short-circuit calculations where requested.
- ISO 9001, ISO 14001 and ISO 45001 certificates.
- Manufacturer authorisation letters for the switchgear brand used.
- Factory test procedure and inspection and test plan.
We cover the general structure of switchgear submittals across all UAE utilities in Preparing switchgear submittals for consultants and utilities.
Where do SEWA submittals get held up?
Most delays come from mismatches: drawings that don't match the single-line diagram, certificates that don't match the offered design, or metering arrangements that don't follow the authority's current drawings.
The issues we watch for before anything leaves our office:
- The MDB's metering CT compartment must follow SEWA's arrangement, not another emirate's. A drawing reused from a Dubai project is the usual culprit.
- Breaker ratings and settings must be identical across the SLD, the GA drawing and the bill of materials.
- The test certificate must cover the board's rated current, short-circuit rating, IP and form.
- Capacitor bank details, where included, must show step sizes, regulator settings and whether reactors are fitted.
- Revisions must be tracked so the consultant can see exactly what changed after each comment.
None of this is complicated, but it is easy to get wrong across fifty boards in a villa community. On large Sharjah developments we produce drawings in EPLAN from a single project database, so a change in the SLD carries through to the schedules and labels.
After approval: manufacture, testing and inspection
Once the consultant and authority approve the submittal, manufacture starts. Delivery is typically about two months after approval, depending on the size of the order and component availability.
Every board goes through routine tests before dispatch: visual and mechanical inspection with torque marking, insulation resistance at 1000 V DC, a 2.5 kV dielectric test for one minute, and function tests. The board leaves with a signed factory test certificate, and the consultant or contractor can witness the tests. Site inspection and energisation then follow SEWA's own procedure for the connection.
Our registrations, type-test certificates and ISO certificates are on the certificates page, and our Sharjah projects are on the projects page.
Frequently asked questions
Can any panel builder supply switchgear for a SEWA project?
Generally no. SEWA expects LV switchgear on its network to come from assemblers it has registered for the relevant category and rating. Before placing an order, check that the panel builder's registration covers the boards on your single-line diagram, and confirm the current requirement with SEWA and the project consultant, since rules can change.
What rating does Al Qudrah's SEWA registration cover?
Al Qudrah Switchgear is a SEWA Certified Company, Grade 1, for switchgear assembly and capacitor bank components up to 3200 A. This matches our IEC 61439-2 verified MDB designs, which are tested up to 3200 A with a short-circuit withstand of 65 kA for 3 s. Copies of the registration are available on request.
How long does approval take before manufacturing starts?
It depends on the consultant's review cycle and the authority's workload, so we can't give a fixed time. What we can control is the quality of the first submission. A complete, consistent submittal usually avoids second and third review rounds. After approval, delivery is typically about two months, depending on order size.
Can the consultant witness factory tests on SEWA panels?
Yes. Consultants and contractors can witness routine tests at our Sharjah factory in Emirates Industrial City. We run insulation resistance at 1000 V DC, a 2.5 kV dielectric test for one minute and function tests, and issue a signed test certificate for each board. Let us know in advance so we can schedule the witness.