A switchgear submittal is the package that lets a consultant, and then the utility, confirm that the boards you plan to build meet the specification before manufacture starts. A good one answers every question the reviewer will ask in the order they will ask it: who is building the boards, what exactly is being built, and what proves it will perform. At Al Qudrah Switchgear in Sharjah, UAE, we prepare these packages for projects under DEWA, SEWA, ADDC and Etihad WE, and this is the structure we use.
What is a switchgear submittal for?
It lets the consultant check compliance on paper while changes are still cheap. Once copper is cut and breakers are mounted, every comment costs time and money.
The consultant reviews the submittal against the specification and the single-line diagram, and marks it with a status such as approved, approved with comments, or revise and resubmit. Depending on the emirate and the board type, the utility may then review the parts that concern it, typically metering, the incoming arrangement and the panel builder's registration. Each utility has its own requirements and they change over time, so the current consultant and authority checklists always come first.
Part 1: company and compliance documents
Start with the documents that show the panel builder is qualified to build these boards. A reviewer who doubts the builder will not spend time on the drawings.
- Trade or industrial licence.
- Utility registration for the relevant emirate and rating. Al Qudrah is a SEWA Certified Company, Grade 1, up to 3200 A.
- Other registrations the project needs, such as the Sharjah Directorate of Public Works or the UAE Ministry of Energy and Infrastructure supplier lists.
- ISO 9001, ISO 14001 and ISO 45001 certificates.
- Authorisation letter from the switchgear brand, for example a Schneider Electric, Legrand, Eaton or CHINT panel builder accreditation.
- A clause-by-clause compliance statement against the specification, with every deviation stated openly.
The compliance statement is where many submittals go wrong. "Complied" against every clause, with no detail, invites a second look at everything. Stating deviations clearly, with the reason and an alternative, builds trust and usually gets a faster answer.
Part 2: technical drawings
The drawings define exactly what will be built. They need to agree with each other down to breaker ratings and settings, because reviewers cross-check them.
| Drawing | What the reviewer checks |
|---|---|
| Single-line diagram | Incomers, couplers, feeders, ratings, breaking capacity, protection settings, metering |
| General arrangement (GA) | Dimensions, section layout, cable entry, IP, form of separation, door devices, weight |
| Busbar arrangement | Busbar size, material and finish, position of neutral and earth bars |
| Schematic and wiring diagrams | Control circuits, interlocks, ATS logic, metering and alarms |
| Nameplate and labelling schedule | Circuit names matching the consultant's drawings, language requirements |
| Foundation or plinth details | Fixing points, cable trench and clearances for the electrical room |
We draw in EPLAN, which keeps the SLD, schematics and schedules linked, and use Legrand XL PRO³ for layout and heat calculation on XL³ boards.
Part 3: calculations and test evidence
The calculations and certificates prove that the board will carry its load and survive a fault. This is the part an experienced consultant reads most carefully.
- IEC 61439-2 design verification certificates and the full test reports, covering the offered rated current, short-circuit rating, IP and form.
- Busbar sizing and short-circuit withstand calculations where the specification asks for them.
- Temperature-rise or heat dissipation calculations, with the ambient used stated clearly.
- Selectivity and cascading tables from the breaker manufacturer.
- For capacitor banks: kvar calculation, step arrangement, regulator settings and harmonic assessment if detuning is proposed.
Our verified designs cover up to 3200 A, 65 kA for 3 s with a 143 kA peak, verified at 50 °C ambient. When the project's values fall inside those limits, we show the comparison in a short table so the reviewer can see it in one look. Our article on IEC 61439-2 design verification explains what to look for in those certificates.
Part 4: catalogues, test plan and samples
Close the package with product data and the plan for factory testing. This tells the consultant what devices are inside and how quality will be checked before dispatch.
Include data sheets for the main devices (ACBs, MCCBs, contactors, meters, relays, capacitors and reactors), marked up to show the exact model offered. Add the factory acceptance test procedure with acceptance criteria and the inspection and test plan with hold and witness points. Our routine tests include insulation resistance at 1000 V DC, a 2.5 kV dielectric test for one minute, function tests and torque marking checks, with a signed certificate for each board.
Utility differences across the UAE
The core package is the same everywhere, but DEWA, SEWA, ADDC and Etihad WE each set their own requirements for metering, registration, drawing format and inspection. The consultant and the authority decide what applies to your project.
Things that commonly differ: the meter and CT compartment layout, the approved list of panel builders, the forms and stamps required on drawings, and the inspection steps before energisation. Reusing a submittal from another emirate without checking these is the most reliable way to collect a "revise and resubmit". For Sharjah specifics, see SEWA approval for LV panels.
Our certificates and registrations are on the certificates page.
Frequently asked questions
What is the most common reason a switchgear submittal is rejected?
Inconsistency. The SLD shows one breaker rating, the GA drawing another, and the bill of materials a third. The second most common reason is a type-test certificate that does not cover the offered design, for example a lower short-circuit rating or a different enclosure system. Cross-checking every document before submission avoids most rejections.
Do I need separate submittals for the consultant and the utility?
Usually the consultant reviews the full package first, and the utility reviews the parts that concern its network, such as metering, the incoming arrangement and the panel builder's registration. The format, stamps and forms for the authority stage vary between DEWA, SEWA, ADDC and Etihad WE, so check the current requirements for your emirate.
Should the submittal include the full type-test report?
Yes, or at least have it ready on request. A certificate cover page shows the headline ratings, but the full report shows the tested configuration: busbar size, enclosure system, ambient, IP and test duration. Experienced consultants ask for it, and providing it upfront saves a review cycle.
How should deviations from the specification be shown?
List every deviation in the compliance statement, with the clause number, what is offered instead, and why. Where possible, show that the alternative performs equal or better. Hidden deviations found later at the factory acceptance test cause far more delay than deviations stated openly at submittal stage.